Project: MattJ   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Matt Jakus   -  
Project:   The Airplane Factory - Sling TSi   -   VIEW REPORTS
Total Hours:1190.7
Start/Last Date:Dec 01, 2019 - Jan 29, 2023
Engine:Rotax 915is
Panel:Garmin 3X
 
Friendly URL: https://eaabuilderslog.org?s=MattJ

Home or Last Project Picture

Nov 28, 2020     Prelim work on Firewall - (9.0 hours)       Category: Firewall
11/26/2020

Not all the cutouts were current form the summer and TAF has a much better diagram guide for it. I permanently mounted the firewall shield to the firewall.


7/22/20 Made a template of the fire wall and made cutouts. Reinstalled the engine mount. Had to adjust for the missing parachute brackets. I ordered the aircraft without a parachute but they sent me the hardware for the parachute Brackets. No big deal just shorter bolts.

The main section of the firewall blanket is not attached to the frame just yet. I will made a few known cutouts but I will wait for the engine/prop kit to get a more accurate sense of the additional cutouts required.


7/17/20Removed engine mount to start the preparation of the firewall. Installed some rivnuts and reviewed the heater installation behind the firewall and the coolant hoses that go through.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.